Capital Improvements Underway in Harborfields

Multiple projects around the district, including the library renovation, scoreboard and ground breaking at WDPS. thumbnail188381

As part of the voter-approved 2019 Capital Improvements Bond Project, construction work has been ongoing this summer throughout the Harborfields Central School District.

Districtwide mechanical projects have been moving along at Harborfields High School, Oldfield Middle School, Thomas J. Lahey Elementary School and Washington Drive Primary School. Air conditioning is set to be functioning in the buildings’ gyms by the end of August. Additionally, security vestibules at the high school and middle school are well underway.

At Harborfields High School, the library demolition was completed and sheetrock and ceiling work are progressing nicely.  The scoreboard for the turf field was delivered and installed in July. Additionally, the bathroom renovation projects are expected to be completed at the end of August.

At Thomas J. Lahey Elementary School, the library demolition is complete with most casework expected to arrive late this month. The bathroom renovation and the science room have expected end of August completion dates.

The Oldfield Middle School library renovation will commence in early August and is expected to be to be completed in mid-fall.

At Washington Drive Primary School, ground was broken for the play area in early July. Concrete will be poured and a basketball hoop will be installed while the district awaits the delivery of the sports court surface material.

The board of education and administration would like to thank the community again for its continued support. The Harborfields School District looks forward to providing students, staff and families with updated and efficient facilities.