Planning for Continued Excellence
The Bond Project is broken into three phases – Phase 1, Phase 2, and Phase 3.
Phase 1 construction: Anticipated to start late fall/early winter through summer 2025.
Click below to see the progress of Phase 1 projects!
Click here for additional information on the Bond Project and Timeline.
April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.
March 2025 – Work has started!
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.
April 2025 – Work has started!
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.
April 2025 – Work has started!
April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.
March 2025 – Work has started!
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.
April 2025 – Work has started!
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.
April 2025 – Work has started!